Project Planning

/ /
Planning vs. Action
What is your bias today? To spend time planning can take away from getting work accomplished. But taking action without planning sufficiently leads to unwanted results such as cost overruns, late delivery, and the like.

Furthermore, planning once and not adjusting to reality can cause disjointed results. Project planning is not a one time event; it requires attention to a living project plan.
Do you need to revise your planning document(s)? Try these tests:
Slippage Recasting 
 All schedules slip (or the maintainer is lying, some would say). As the "actual" strays from the "planned" schedule, you use up buffer time, or compress events that now need to happen faster. Perhaps it is time to recast the schedule in light of the cumulative slippages, changes, and new information on progress (positive and negative).
Updated Risk Assessment
It is very hard to imagine yourself and your team in the future - weeks or months out - and think of all of the risks you will face at that moment in the project's lifecycle. Do you feel comfortable - and does your team - with the risk management and mitigation plans in place, or has it been a while since they were revisited?
Big Chunks vs. Little Chunks
Have you broken down your project - "chunking" to durations of one- or two-week periods? If not, then outside of a long multi-year project, you should work on breaking down your chunks into smaller units that are planned in smaller time increments.
Time since latest plan revision, or status meeting
How long has it been since you revised your schedule in terms of the length of the project? If over 10% of the project duration has lapsed, have a review of the plan - include knowledgable team members if appropriate. If your project timeline has advanced 10% since your last status meeting, make sure that your plan is still valid. Base your assessment on the expected accomplishments, and also on feedback from the team regarding new details information on progress and on unexpected events. Revising a plan without reaching out to the team can be similar to walking in a dark field using the memory of your last daytime walk-through.
The project manager has three main areas to plan: Time, Scope, and Cost (financial). Maintain updates to your planning - keeping current between these main areas - to keep plans balanced, realistic, and in sync. Remember that each project is unique, and tailor your planning and frequency of updates based on the needs of the task at hand.